Standard Interconnection Agreement

Submittal Requirements

  • Single-Line Diagram
  • Relay List (if applicable)
  • Trip Scheme (if applicable)
  • Three-Line Diagram (systems >= 30 kW)
  • Completed Exhibit A
  • Completed Signature Page - Appendix II or Appendix II-A

PV Inspection

Prior to operating your system continuously, an inspection is required to verify compliance with our Standard Interconnection Agreement Rule 14H.

Scheduling of the test requires a two (2) week lead time.

The inspection will verify the following at a minimum:

  • The installation, including equipment ratings, matches the issued Single Line Diagram.
  • The Inverter(s) meet UL-1741 standard nameplate.
  • The manual disconnect switch is properly labeled.
  • Anti-islanding - The customer simulates a "loss of utility" power to the system by opening the disconnect switch or breaker. The customer must have a qualified person to operate the disconnect and demonstrate a visible break.*

* For liability purposes Hawaii Electric Light Company, Inc. will not operate your equipment and so we ask that you provide a qualified person/electrician to be available to conduct the test.


Forms

2 Party Agreement <10 kW - To access Exhibits A - D and Signature Page

2 Party Agreement >10 kW - To access Exhibits A - D and Signature Page

3 Party Agreement <10 kW - To access Exhibits A - D and Signature Page

3 Party Agreement >10 kW - To access Exhibits A - D and Signature Page

Appendix II-B (Non-Exporting Distributed Generation - Momentary Parallel Operation)

Other

Distributed Energy Resource Application Submittal Form (SIA)

Distributed Energy Resource Validation Form

Distributed Energy Resources 90-Day Extension Request Form

Distributed Energy Resources Application Withdrawal Form


Submit Forms

Via United States Postal Service:
Hawaii Electric Light
ATTN: Standard Interconnection Agreement; Engineering
P.O. Box 1027
Hilo, HI 96721-1027